P
PK Consulting
We have the following situation:
1 - We are SP2 on the clients, with whatever was before SP2A on the servers
2 - Our tasks are fixed duration, effort driven off, no constraints
3 - We use managed time frames.
4 - We experience two problems. First, we complete a task with no time
recorded against (via PWA) by removing the resources and updating the %
complete. After publishing, we sync with protected acutals and the %
completion values are set to zero. Second, we sometimes complete tasks with
time recorded against them (via PWA) by setting remaining duration to zero.
While this updates the % complete to 100%, we sometimes get the dreaded out
of sync message.
Any ideas?
PK Consulting
1 - We are SP2 on the clients, with whatever was before SP2A on the servers
2 - Our tasks are fixed duration, effort driven off, no constraints
3 - We use managed time frames.
4 - We experience two problems. First, we complete a task with no time
recorded against (via PWA) by removing the resources and updating the %
complete. After publishing, we sync with protected acutals and the %
completion values are set to zero. Second, we sometimes complete tasks with
time recorded against them (via PWA) by setting remaining duration to zero.
While this updates the % complete to 100%, we sometimes get the dreaded out
of sync message.
Any ideas?
PK Consulting