kinetix
Didn't get any responses to a previous post on this. I would like to b
able to show a "simple" % complete. It can be based on elapsed % (as o
data date) of total planned duration. Sometimes I would prefer to punc
in a %. If I do that now, it changes the end dates and that's not okay
This shouldn't be difficult but it's eluding me. thank