V
Verossa
Morning All,
I have a fixed duration task from 12/05/04 - 01/06/04 involving 20hrs work.
I input work in the task usage view on a monthly basis. When I add 11 hrs for May the % complete equals 93%. It should be 55%.
I've moved the date 10/05/04 - 28/05/04 just to see if the % complete changes as I understand this is effected by the duration and it remains at 93%.
Why is this happening?
TIA to all who respond,
Vers
I have a fixed duration task from 12/05/04 - 01/06/04 involving 20hrs work.
I input work in the task usage view on a monthly basis. When I add 11 hrs for May the % complete equals 93%. It should be 55%.
I've moved the date 10/05/04 - 28/05/04 just to see if the % complete changes as I understand this is effected by the duration and it remains at 93%.
Why is this happening?
TIA to all who respond,
Vers