% Complete

K

Karen

My % Complete column is missing - How do I add this column? I added a column
and changed the column heading to % Complete and now there are just auto
numbers in each row - 1, 2, 3, 4, etc.

HELP
 
B

Brian K - Project MVP

Karen said:
My % Complete column is missing - How do I add this column? I added
a column and changed the column heading to % Complete and now there
are just auto numbers in each row - 1, 2, 3, 4, etc.

HELP

Right click on the column header that is just to the right of where you
want the new column to be. Then click Insert Column. From the drop down
list pick "% Complete" and then click OK

--
___
Brian K
Project MVP
Project MVP
http://www.projectified.com

Project Server Consultant
http://www.quantumpm.com
 
J

JulieS

Hi Karen,

You are almost there. Click your secondary mouse button in an existing
column heading and choose Insert Column from the shortcut menu. In the Column
Definition dialog box, click the drop down in the Field Name box and scroll
all the way to the top. The %Complete and %Work Complete fields are at the
top. Select the field and click the OK button to insert the field to the left
of the column you selected in the table.

Hope this helps. Let us know how you get along.
Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question