J
jimbudde
The following is posted on behalf of a coworker. If it's not clear, I
apologize.
I apologize in advance if this question has been asked before, but I
couldn't find it.
I am using Project Server and Project Professional 2003. The issue that
I am experiencing is "Remaining Work" shows up as incomplete in the
Resource Usage View on completed projects when viewed from a different
project.
For example, if project ABC is completed by marking all tasks within it
as 100% complete, then remaining work is displayed in the Resource
Usage View within Project ABC as zero. Project ABC is then Published
to update the server. When viewing project XYZ that are using
resources from Project ABC the resource levelling is showing resources
as over-allocated. Upon further investigation, it appears the
overallocation is coming from the fact that the server still has
Reamining Work assigned to these resources.
How can I correct this? How does this effect Resource Leveling, since
in at least one view, there is "Remaining Work." Would resource
levelling the completed project help to clear out any possible bad data
on the server?
apologize.
I apologize in advance if this question has been asked before, but I
couldn't find it.
I am using Project Server and Project Professional 2003. The issue that
I am experiencing is "Remaining Work" shows up as incomplete in the
Resource Usage View on completed projects when viewed from a different
project.
For example, if project ABC is completed by marking all tasks within it
as 100% complete, then remaining work is displayed in the Resource
Usage View within Project ABC as zero. Project ABC is then Published
to update the server. When viewing project XYZ that are using
resources from Project ABC the resource levelling is showing resources
as over-allocated. Upon further investigation, it appears the
overallocation is coming from the fact that the server still has
Reamining Work assigned to these resources.
How can I correct this? How does this effect Resource Leveling, since
in at least one view, there is "Remaining Work." Would resource
levelling the completed project help to clear out any possible bad data
on the server?