Carla Evans
I'm a new Administrator in Project Server 2007. Our completed tasks are
defaulting to drop off the assigned My Tasks page after 10 days, according to
the Task Settings & Display, Current Task View definition. However, I'm
being notified by web access users and project managers alike that completed
tasks (0 remaining work) that has been accepted by the project managers
(saved, published and checked back in) is still continuing to appear. Any
ideas what other settings I might research?