Completed task still at Current tasks

P

Perl

Hello,

We have Project Server 2007.
Our team member reported actual work and completed for tasks but they still
see those tasks at the current tasks view.

Any idea ?

Perl
 
D

Dale Howard [MVP]

Perl --

If your TM has the Current Tasks option selected on the My Tasks page, then
the completed tasks will continue to show for 10 days, after which the
system will hide them. The Project Server administrator defines what
constitutes a "current" task, and the default value is 10 days. Can you
confirm that the TM has Current Tasks option enabled? If so, ask your
Project Server administrator is the definition of a current task is
different from the 10 days default value. Hope this helps.
 
J

Jonathan Sofer

Did the PM also republish the project after accepting the updates? Are the
assignments showing as 100% complete on the My Tasks page.

Also, is the task 100% complete are is there still some remaining work to be
done by some of the resources assigned to that task?

Jonathan
 