Hi,

We are using project server 2003 and are using timesheets to record time.
The issue I’m having is that tasks appear in task list that are not 100%
completed by the person but are 100% completed on the project.

How do I stop the task appearing in the task list?

Thanks in advance
 
D

Dale Howard [MVP]

Taj --

It sounds like the PM has manually updated the % Complete value to 100% on
some of the tasks in the Microsoft Project plan. This being the case,
he/she should click Collaborate - Publish - Republish Assignments and select
the "Overwrite actual work..." option. This action will "push" the
completed task information to the relevant team member's View My Tasks page.
Hope this helps.
 
T

Taj

That has done the trick.

Thanks,


Dale Howard said:
Taj --

It sounds like the PM has manually updated the % Complete value to 100% on
some of the tasks in the Microsoft Project plan. This being the case,
he/she should click Collaborate - Publish - Republish Assignments and select
the "Overwrite actual work..." option. This action will "push" the
completed task information to the relevant team member's View My Tasks page.
Hope this helps.
 