Marc
I have noticed that tasks with zero remaining work and that have had no
actuals reported will appear in the current tasks view. I suppose that one
of the criteria for a completed task in MS Project Server is that actuals had
to have been reported to it. Is there a way around this? Can a task be
published, no actual work reported, remaining work set to zero, and the task
not appear when "Current Tasks" is chosen on the Tasks page? Thanks!