S
Stefan Robert
Hi,
is there a way to make MS-Project not change the % completed of a task
when I enter the Actual Work done for that task?
The reason is that when I enter the Actual work done for a task, the
BCWP and ACWP are always identical.
As I beleive, BCWP the (budgeted cost for the task * % completed) and the
ACWP should be the cost of the actual work done, right?
So is there a way to enter the actual work and the % completed as two
different values not related?
Stefan
is there a way to make MS-Project not change the % completed of a task
when I enter the Actual Work done for that task?
The reason is that when I enter the Actual work done for a task, the
BCWP and ACWP are always identical.
As I beleive, BCWP the (budgeted cost for the task * % completed) and the
ACWP should be the cost of the actual work done, right?
So is there a way to enter the actual work and the % completed as two
different values not related?
Stefan