R
RickD
In my baseline schedule I have a split task – call it Early Complete. The
two parts of the Early Complete task straddle the status date. The task has
finished ahead of schedule so I mark it 100% complete. I then “Reschedule
uncompleted work†and the uncompleted tasks split and move up to my status
date as expected. Here is the part I’m not sure how to fix: the uncompleted
tasks are being split around the second half of the Early Complete task.
When I look at the Resource Usage table hours are being allocated to work on
the second half of Early Complete even though Remaining Work is 0. In this
particular case I can reduce the Work so the entire task falls behind my
status date. But for tasks that are completely in the future this technique
would mean setting their Work to zero. Any suggestions?
Thanks in advance,
Rick
two parts of the Early Complete task straddle the status date. The task has
finished ahead of schedule so I mark it 100% complete. I then “Reschedule
uncompleted work†and the uncompleted tasks split and move up to my status
date as expected. Here is the part I’m not sure how to fix: the uncompleted
tasks are being split around the second half of the Early Complete task.
When I look at the Resource Usage table hours are being allocated to work on
the second half of Early Complete even though Remaining Work is 0. In this
particular case I can reduce the Work so the entire task falls behind my
status date. But for tasks that are completely in the future this technique
would mean setting their Work to zero. Any suggestions?
Thanks in advance,
Rick