Completed work

D

Debbie

I am fairly new to Project Server 2007 so excuse me if this is an obvious
question. I have a project plan that has been published to Server and a
resource has entered their time on a task so that PWA shows 100% complete and
no remaining work. The task update has been saved, submitted and approved.
When I open the project plan the % Complete is showing 17% while PWA shows
100%. What am I missing? Any help is appreciated.
 
J

Jonathan Sofer

Make sure you are looking at the same % complete. The resource might have
finished their assignment but the task might have more remaining work from
other resources assigned to the task. Highlight the task and go to the Task
Usage view to get an idea of all the resources and the % completes.

Jonathan
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top