I am fairly new to Project Server 2007 so excuse me if this is an obvious
question. I have a project plan that has been published to Server and a
resource has entered their time on a task so that PWA shows 100% complete and
no remaining work. The task update has been saved, submitted and approved.
When I open the project plan the % Complete is showing 17% while PWA shows
100%. What am I missing? Any help is appreciated.