D
David
For some reason I'm just not getting this. Why can you setup a project with
three task. The first being a prodecessor of the second and the second being
a predecessor of the third. Then someone can go in and apply time to the
third task or even complete it while the first two tasks haven't even been
started?
In PWA, why does the system send an email just becasue the start date is
hit, even if the predecessor's haven't been completed?
Dave
three task. The first being a prodecessor of the second and the second being
a predecessor of the third. Then someone can go in and apply time to the
third task or even complete it while the first two tasks haven't even been
started?
In PWA, why does the system send an email just becasue the start date is
hit, even if the predecessor's haven't been completed?
Dave