S
Snig
Hi
This is the scenario: suppose a task has been alloted 10 hours.
However, in Project Server Resources can put more hours than that. But
whenever the actual hours becomes equal to greater than whatever is
alloted (10 hrs in this case), the task automatically gets completed.
How to block this behavior? I want my project managers to manually flag
the tasks as completed when they are notified.
Thanks in advance.
This is the scenario: suppose a task has been alloted 10 hours.
However, in Project Server Resources can put more hours than that. But
whenever the actual hours becomes equal to greater than whatever is
alloted (10 hrs in this case), the task automatically gets completed.
How to block this behavior? I want my project managers to manually flag
the tasks as completed when they are notified.
Thanks in advance.