C
Chris
I am trying to use the % completed column, but am finding
that the summary levels of % completed are dependent on
the subtasks % completed and their durations.
Is there a simple setting or a different field I should
be using ??
Below is the example from my Project
The answer I expected was
Level 1 6% and the first level 2 25% etc
Cheers
Chris
Level 1 4% Mon 3/05/04 Fri 25/02/05
Level 2 9% Mon 3/05/04 Fri 11/02/05
Level 3 26% Mon 3/05/04 Fri 11/02/05
Level 3 26% Mon 3/05/04 Fri 28/01/05
Level 3 21% Mon 3/05/04 Mon 31/01/05
Level 3 20% Mon 3/05/04 Thu 30/09/04
Level 3 33% Mon 3/05/04 Fri 11/02/05
Level 2 2% Mon 3/05/04 Tue 1/02/05
Level 3 11% Mon 3/05/04 Tue 1/02/05
Level 3 0% Mon 3/05/04 Tue 1/02/05
Level 3 0% Mon 3/05/04 Wed 19/01/05
Level 3 0% Mon 3/05/04 Mon 31/01/05
Level 3 0% Mon 3/05/04 Tue 18/01/05
Level 3 0% Mon 3/05/04 Wed 26/01/05
that the summary levels of % completed are dependent on
the subtasks % completed and their durations.
Is there a simple setting or a different field I should
be using ??
Below is the example from my Project
The answer I expected was
Level 1 6% and the first level 2 25% etc
Cheers
Chris
Level 1 4% Mon 3/05/04 Fri 25/02/05
Level 2 9% Mon 3/05/04 Fri 11/02/05
Level 3 26% Mon 3/05/04 Fri 11/02/05
Level 3 26% Mon 3/05/04 Fri 28/01/05
Level 3 21% Mon 3/05/04 Mon 31/01/05
Level 3 20% Mon 3/05/04 Thu 30/09/04
Level 3 33% Mon 3/05/04 Fri 11/02/05
Level 2 2% Mon 3/05/04 Tue 1/02/05
Level 3 11% Mon 3/05/04 Tue 1/02/05
Level 3 0% Mon 3/05/04 Tue 1/02/05
Level 3 0% Mon 3/05/04 Wed 19/01/05
Level 3 0% Mon 3/05/04 Mon 31/01/05
Level 3 0% Mon 3/05/04 Tue 18/01/05
Level 3 0% Mon 3/05/04 Wed 26/01/05