Very often we need to set more than 1 link between two tasks like a start to
start and a finish to finish.
how do i do this
 
S

Steve House [MVP]

John suggested a hammoxk task. That will work if you need the two tasks in
question start and end together. But hammock tasks are not quite the same
thing as dependency links. If that's what you need, I'm afraid you're out
of luck. While a task may have multiple predecessors and/or multiple
successors, you can't have links driving both the start and finish
separately.
 