S
Sheba Chungath
How can I compute and display SV% and EV% through Gantt Chart and PAW
Schedule variance (SV%) =[ (Actual duration - Baselined duration)/Baselined duration ] * 10
Work variance (EV%) =[ (Actual work- Baselined work)/Baselined work] * 10
I can do SV% easily 'coz there's a field for it
But EV% is proving to be tricky
Please help!!!
Schedule variance (SV%) =[ (Actual duration - Baselined duration)/Baselined duration ] * 10
Work variance (EV%) =[ (Actual work- Baselined work)/Baselined work] * 10
I can do SV% easily 'coz there's a field for it
But EV% is proving to be tricky
Please help!!!