Computing an ddisplaying SV% and EV%

S

Sheba Chungath

How can I compute and display SV% and EV% through Gantt Chart and PAW
Schedule variance (SV%) =[ (Actual duration - Baselined duration)/Baselined duration ] * 10
Work variance (EV%) =[ (Actual work- Baselined work)/Baselined work] * 10

I can do SV% easily 'coz there's a field for it
But EV% is proving to be tricky

Please help!!!
 
J

J Baird

Have you looked at the CV% field?
CV% = [ (BCWP - ACWP) / BCWP ] * 100
BCWP is the budgeted cost of work performed
ACWP is the actual cost of work performed

Some other EV fields you may find useful:
CPI = BCWP / ACWP
SPI = BCWP / BCWS

Regarding the SV% field in MSP, it's both cost and work related, not just
duration:
SV% = ((BCWP - BCWS)/ BCWS) * 100
BCWP is the budgeted cost of work performed
BCWS is the budgeted cost of work scheduled

MSP has some interesting EV Tables. From the Main Menu, you can select
[Views][Tables][More Tables] and you'll see the 'Earned Value' tables in the
list.

MSP can also use the Task [Physical % Complete] field for EV calculations
(this field is sometimes referred to as the "Earned Value % Complete" field.

Sheba Chungath said:
How can I compute and display SV% and EV% through Gantt Chart and PAW?
Schedule variance (SV%) =[ (Actual duration - Baselined
duration)/Baselined duration ] * 100
Work variance (EV%) =[ (Actual work- Baselined work)/Baselined work] * 100

I can do SV% easily 'coz there's a field for it.
But EV% is proving to be tricky.

Please help!!!!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top