Concurrent Calendars

D

David

Is there a way in project professional to have two calendars in on project?

I need to have selected tasks in a schedule to have one calendar, and
another section of tasks with a different calendar. Is there a way to do
this?

David
 
D

Dale Howard [MVP]

David --

Yes. You can set the calendar for scheduling the majority of tasks in the
project by clicking Project - Project Information and then selecting a a
value from the Calendar pick list. You should then select only those tasks
that have an alternate working schedule, click Project - Task Information,
select the Advanced tab, and select a Calendar value. Depending on your
situation, you may also want to select the "Scheduling ignores resource
calendars" option on the Advanced page as well. Hope this helps.
 