S
Sandy82
Hello there
Please could an expert help with my question?
I am a project coordinator with the responsibility of updating a large
project plan (436 tasks) for the project manager. The task status
information is sent to me from various departments.
If I add information which changes dates to a task which has successors, is
it possible to apply conditional formatting to the successors' start and
finish date columns that will indicate if a date has changed? (At present I
have to scroll up and down to each successor task and compare their dates
with a hard copy of the plan).
Many thanks.
Please could an expert help with my question?
I am a project coordinator with the responsibility of updating a large
project plan (436 tasks) for the project manager. The task status
information is sent to me from various departments.
If I add information which changes dates to a task which has successors, is
it possible to apply conditional formatting to the successors' start and
finish date columns that will indicate if a date has changed? (At present I
have to scroll up and down to each successor task and compare their dates
with a hard copy of the plan).
Many thanks.