Configuring tasks in weeks not days

S

Steve House [MS Project MVP]

Simply enter the durations in weeks. An entry of 3m is minutes, 3h is
hours, 3d is days, 3w is weeks, and 3mon is months.
 
R

Rob Schneider

If you wish to define the task duration or work in weeks, type in a "w"
after the number, e.g. "72w" for 72 weeks.

Hope this is useful to you. Let us know.

rms
 
J

JulieD

Hi

in addition to the other comments, be aware that Project still thinks in
minutes and takes your definition of a week from what is entered under tools
/ options / calendar. It is important to ensure that you have the right
definition for a week before you enter any tasks using "weeks" as a
duration.

Cheers
JulieD
 