M
mttakimbo
We have several types of task that need a "Finish No Later Than"
contstraint. I'm not sure how to get Project to reallocate resources
when the task is started later than expected.
For example, let's say we have a task that that must be complete by
10/24. We want to plan on having one resource work on it 2h a day for
10 days, starting on 10/11. This is 25% of the resource's units.
Now let's say that the first time the resource works on this task is
4h on 10/15, which is 2h behind schedule. When this is entered on the
timesheet, the Project Planning Wizard pops up stating that this will
create a scheduling conflict, because the program wants to push the
task finish date out another day.
Since my resource is only scheduled at 25% for the remainder of the
task (and is not scheduled in any other tasks or projects), why
doesn't Project just reallocate the resource to make up those 2h
during the remainder of the task?
Am I missing something?
The task is set as Fixed Work.
Thanks in advance,
Brian
contstraint. I'm not sure how to get Project to reallocate resources
when the task is started later than expected.
For example, let's say we have a task that that must be complete by
10/24. We want to plan on having one resource work on it 2h a day for
10 days, starting on 10/11. This is 25% of the resource's units.
Now let's say that the first time the resource works on this task is
4h on 10/15, which is 2h behind schedule. When this is entered on the
timesheet, the Project Planning Wizard pops up stating that this will
create a scheduling conflict, because the program wants to push the
task finish date out another day.
Since my resource is only scheduled at 25% for the remainder of the
task (and is not scheduled in any other tasks or projects), why
doesn't Project just reallocate the resource to make up those 2h
during the remainder of the task?
Am I missing something?
The task is set as Fixed Work.
Thanks in advance,
Brian