PWA and Project Pro. shows different values on the task status of certain task.
Question no. 1:
If there are more than resources in a task (i.e Task 1 has Person 1 and
Person 2), is the task status equal to the average of task update the Persons
has inputed. If Person 1 = 50% and Person 2 = 70% so Task 1 is 60% complete
(average of 70 & 50)???
Question no. 2:
Will having more than two task of the same name cause conflict on showing
the current status of the task? i.e.
Phase1
Code
Debug
Phase2
Code
Debug
We were having issues because there were times when Phase1-Code shows the
averaga of Phase1-Code and Phase2-Code task.
Any help on this ???
Question no. 1:
If there are more than resources in a task (i.e Task 1 has Person 1 and
Person 2), is the task status equal to the average of task update the Persons
has inputed. If Person 1 = 50% and Person 2 = 70% so Task 1 is 60% complete
(average of 70 & 50)???
Question no. 2:
Will having more than two task of the same name cause conflict on showing
the current status of the task? i.e.
Phase1
Code
Debug
Phase2
Code
Debug
We were having issues because there were times when Phase1-Code shows the
averaga of Phase1-Code and Phase2-Code task.
Any help on this ???