R
Ron
Hi,
I am trying to set up my scedule based on an 6 hr day rather than an 8
hr. I have done the following
New base calendar called "6 hour day"
9:00am - 12 noon
1:00pm - 4pm
In the options I have
Default start 9:00am
Defauly finish 4:00pm
Hours per day 6
Hours per week 30
Days per month 17
I set up a resource to use "6 hour day" as the base calendar
I would expect that the task would finish on day 2 at 4pm but it
finished at 3pm. Looking at the Gannt chart shows day 2 has working
time commencing at 8am rather than at 9am as specified in the
calendar.
Any ideas as to what I am doing wrong would be appreciated.
Ron
I am trying to set up my scedule based on an 6 hr day rather than an 8
hr. I have done the following
New base calendar called "6 hour day"
9:00am - 12 noon
1:00pm - 4pm
In the options I have
Default start 9:00am
Defauly finish 4:00pm
Hours per day 6
Hours per week 30
Days per month 17
I set up a resource to use "6 hour day" as the base calendar
I would expect that the task would finish on day 2 at 4pm but it
finished at 3pm. Looking at the Gannt chart shows day 2 has working
time commencing at 8am rather than at 9am as specified in the
calendar.
Any ideas as to what I am doing wrong would be appreciated.
Ron