I work on Ms-Project server 2007. My organzation's working time is 7.5hours a
day.
What I did:
1- From <PWA> choose <Server Setting>, Open <Enterprise Calendars>,create a
new enterprise calendar
2- From <Project Professional: Enterprise Option> open <Enterprise Global>.
From <Tools menu> select <Change working time>
3- Select created new enterprise calenda, open <options>, change:
- Default Start time 8:00 AM
- Default End time 4:30 PM
- Hours per day: 7.5 hours
- Hours per week: 37.5 hours
4- <Save as default>,then save <Enterprise Global> and Check-in it.
Then:
1- I created a project base on this new enterprise calenda,
2- Created a task for duration 1 day,
3- Assigned a resource to this task (resource base calendar is same 'new
enterprise calendar')
4- Published this project.
The problem is:
1- From <Project Professional - Gantt Chart view>, the duration of the task
is 1 day but on <PWA_My assignments> view, the duration of this task is 0.94
days,
2- From <Project Professional _ Resource Usage view>, when I add <Remaining
Availablity> line, it shows 8 hours but not 7.5 hours on free day as defined
Who could help me for this case? On which parameters should I configure?
Thanks in advance.
JJin
day.
What I did:
1- From <PWA> choose <Server Setting>, Open <Enterprise Calendars>,create a
new enterprise calendar
2- From <Project Professional: Enterprise Option> open <Enterprise Global>.
From <Tools menu> select <Change working time>
3- Select created new enterprise calenda, open <options>, change:
- Default Start time 8:00 AM
- Default End time 4:30 PM
- Hours per day: 7.5 hours
- Hours per week: 37.5 hours
4- <Save as default>,then save <Enterprise Global> and Check-in it.
Then:
1- I created a project base on this new enterprise calenda,
2- Created a task for duration 1 day,
3- Assigned a resource to this task (resource base calendar is same 'new
enterprise calendar')
4- Published this project.
The problem is:
1- From <Project Professional - Gantt Chart view>, the duration of the task
is 1 day but on <PWA_My assignments> view, the duration of this task is 0.94
days,
2- From <Project Professional _ Resource Usage view>, when I add <Remaining
Availablity> line, it shows 8 hours but not 7.5 hours on free day as defined
Who could help me for this case? On which parameters should I configure?
Thanks in advance.