R
RiiDii
Hi all,
I'm quite new to Project and have searched long to find a solution for
my seemingly simple dilemma, but I can't seem to find any that apply.
Say, for instance, that I have a project which calls for three
employees to work on six tasks, but each worker shouldn't exceed about
10 hours a week.
I am trying to determine how to configure Project so that each employee
does not work over 10 hours a week; if a task has a duration of 1 week
and I assign a resource then their total work should indicate 10 hours.
If a task says 12 hours, it should take the resource more than a week to
complete it.
If I change the Calendar tab of the Options window so that no employee
can work more than 2 hours a day or 10 hours a week, all of the entered
durations drastically increase as a result. Again, and it is kind of
hard to explain, but I am trying to figure out the best way to restrict
a worker from exceeding 10 hours per week. If I decrease their Max
Units down to 25% and assign them to a 1 wk task, they still register as
having to work 40 hours. Many thanks in advance.
I'm quite new to Project and have searched long to find a solution for
my seemingly simple dilemma, but I can't seem to find any that apply.
Say, for instance, that I have a project which calls for three
employees to work on six tasks, but each worker shouldn't exceed about
10 hours a week.
I am trying to determine how to configure Project so that each employee
does not work over 10 hours a week; if a task has a duration of 1 week
and I assign a resource then their total work should indicate 10 hours.
If a task says 12 hours, it should take the resource more than a week to
complete it.
If I change the Calendar tab of the Options window so that no employee
can work more than 2 hours a day or 10 hours a week, all of the entered
durations drastically increase as a result. Again, and it is kind of
hard to explain, but I am trying to figure out the best way to restrict
a worker from exceeding 10 hours per week. If I decrease their Max
Units down to 25% and assign them to a 1 wk task, they still register as
having to work 40 hours. Many thanks in advance.