J
J. Belcher
Say that I estimate a task to take 3.5 hours to complete. The resource
assigned that task finishes the task, but it only took him/her 0.5 hours to
complete. How can you record this under actual time and still have 100%
completion?
In other words, if I mark 3.5 hours of work and 0.5 hours of actual work, %
complete will reflect 14% complete. If I try to manually set that as 100%
complete, it will change the values for work/actual work.
How do you handle these cases?
assigned that task finishes the task, but it only took him/her 0.5 hours to
complete. How can you record this under actual time and still have 100%
completion?
In other words, if I mark 3.5 hours of work and 0.5 hours of actual work, %
complete will reflect 14% complete. If I try to manually set that as 100%
complete, it will change the values for work/actual work.
How do you handle these cases?