A
awmccready
If I establish a finish-to-start link at the summary level, then that link
should be consistently enforced by MS Project at the subordinate task level.
For example, if I have a resource of type work assigned to tasks subordinate
to each of two summary levels, then I currently get an incorrect
overallocation for that resource, even though that resource has sufficient
remaining time available to work. To remove the overallocation, I must
establish a direct finish-to-start link between the task in the predecessor
summary level and the task in the successor summary level. Only then does MS
Project schedule the subordinate task in the successor summary level to start
after the other task has finished. The finish-to-start link at the summary
level was ignored. This behavior may currently only exist when the two tasks
involved are scheduled by MS Project to occur on the same day.
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...0070d77&dg=microsoft.public.project.developer
should be consistently enforced by MS Project at the subordinate task level.
For example, if I have a resource of type work assigned to tasks subordinate
to each of two summary levels, then I currently get an incorrect
overallocation for that resource, even though that resource has sufficient
remaining time available to work. To remove the overallocation, I must
establish a direct finish-to-start link between the task in the predecessor
summary level and the task in the successor summary level. Only then does MS
Project schedule the subordinate task in the successor summary level to start
after the other task has finished. The finish-to-start link at the summary
level was ignored. This behavior may currently only exist when the two tasks
involved are scheduled by MS Project to occur on the same day.
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...0070d77&dg=microsoft.public.project.developer