S
Schalkje
I'm looking for a method to implement constraining resources using Project
2007.
I know of a solution from an oil company, using beds as a resource. Beds are
added by a macro in Project Professional, at each task, equal to the number
of resources.
This way the beds (a fixed number of beds are available on an oil platform)
can be used in the leveling process, assuring that there are never more
people on the platform than there are beds available.
One important restriction of this solution is that you have to use fixed
duration, to make it usefull.
I’m currently doing an implementation for an oilplatform. And we want to use
available beds as a constraining resource on the leveling process.
But we want to use “fixed work†as a planning principle.
Thanks,
Jeroen Schalken
2007.
I know of a solution from an oil company, using beds as a resource. Beds are
added by a macro in Project Professional, at each task, equal to the number
of resources.
This way the beds (a fixed number of beds are available on an oil platform)
can be used in the leveling process, assuring that there are never more
people on the platform than there are beds available.
One important restriction of this solution is that you have to use fixed
duration, to make it usefull.
I’m currently doing an implementation for an oilplatform. And we want to use
available beds as a constraining resource on the leveling process.
But we want to use “fixed work†as a planning principle.
Thanks,
Jeroen Schalken