A constraint such as Finish no later than or must finish on can or will
influence the calculated dates.
A deadline will not, it will just show an indicator when teh finish date
exceeds the deadline
HTH
Yep - a deadline on a task effects the slack time calculations in the
project exactly as would a FNLT constraint of the same date on the task.
Steve