G
giovanni.ciceri
Hallo,
I've setted on some activities the contraint "Finish no Later Then", but
when I try to update the no completed and not began to work activities,
MS-Project shows an error that said that if I want to reschedule the work
with the date of today, I've to eliminate the constrait "Finish no Later
Then" and set the constrait "As soon as possible". Why? I want to reschedule
the activities of the project with the costrain "Finish no Later Then".
Thanks for any suggestion,
gio
I've setted on some activities the contraint "Finish no Later Then", but
when I try to update the no completed and not began to work activities,
MS-Project shows an error that said that if I want to reschedule the work
with the date of today, I've to eliminate the constrait "Finish no Later
Then" and set the constrait "As soon as possible". Why? I want to reschedule
the activities of the project with the costrain "Finish no Later Then".
Thanks for any suggestion,
gio