I have a project which several people work on. I have set constraints where
it must start on a certain date. However, lets say it must start on July 1,
and today is May 15 they can still go in and mark it 100% complete. Why is
that?
I want them to only be able to mark the task 50% or 100% on the date they
should be starting on it, not before hand. If they are able to mark a task
complete, and I assume it is done, when in reality it isnt, I run into major
problems.