Construction project.MS Project Proffessional 2003.

S

smumrik

Hello, I have a problem.

We run a construction project.
There is a project have task «to build foundation». It's planned duration -
30 days, for example.
The workers build several cubic meters of concrete every day.
In end day they must input remaining work in cubic meter in MS Project
Professional 2003.
I know the total work planned for the task is 300 cubic metre.
Project manager also needs to get the information on a percent of work
performed and completed for this task every day.

What shoukd I do to create a MS Project view for workers and what's I must
create view to computing a percent of work complete for this task?
What fields should I create for the task to get such results?
 
M

Mike Glen

Hi smumrik ,

Try posting on the server newsgroup as this one is closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP
 
S

smumrik

Hi Mike,

When i can ask my question?
Give me link to server newsgrous when have topics about MS Project
Proffesional and Ms Project Server 2003.

Best regards.

"Mike Glen" пишет:
 
J

JulieS

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top