Hello, I have a problem.
We run a construction project.
There is a project have task «to build foundation». It's planned duration -
30 days, for example.
The workers build several cubic meters of concrete every day.
In end day they must input remaining work in cubic meter in MS Project
Professional 2003.
I know the total work planned for the task is 300 cubic metre.
Project manager also needs to get the information on a percent of work
performed and completed for this task every day.
What shoukd I do to create a MS Project view for workers and what's I must
create view to computing a percent of work complete for this task?
What fields should I create for the task to get such results?
We run a construction project.
There is a project have task «to build foundation». It's planned duration -
30 days, for example.
The workers build several cubic meters of concrete every day.
In end day they must input remaining work in cubic meter in MS Project
Professional 2003.
I know the total work planned for the task is 300 cubic metre.
Project manager also needs to get the information on a percent of work
performed and completed for this task every day.
What shoukd I do to create a MS Project view for workers and what's I must
create view to computing a percent of work complete for this task?
What fields should I create for the task to get such results?