M
Markarina
Having read various posts on contingency and hammock tasks, I have
done the following which is probably 90% of the way there to what I am
trying to achieve.
In a single MPP file I have my project plan with all it's tasks I have
then added another project within the same file to hold the
contingency "pot", within that mini project I have a milestone task
linked to the end of the project a "contingency used" task and a
"contingency remaining" task, the contingency remaining task is
"hammocked" between the contingency used and end of project milestone,
such that when I increase the contingency used work the contingency
remaining shrinks accordingly - this all works wonderfully. What I was
wondering is it possible to go one better and have the value for
contingency used to update automatically when the actual hours worked
for a task in the main plan exceeds the allocated work hours ?
For reference I'm using MSP 2007 with fixed units tasks.
thanks
Mark
done the following which is probably 90% of the way there to what I am
trying to achieve.
In a single MPP file I have my project plan with all it's tasks I have
then added another project within the same file to hold the
contingency "pot", within that mini project I have a milestone task
linked to the end of the project a "contingency used" task and a
"contingency remaining" task, the contingency remaining task is
"hammocked" between the contingency used and end of project milestone,
such that when I increase the contingency used work the contingency
remaining shrinks accordingly - this all works wonderfully. What I was
wondering is it possible to go one better and have the value for
contingency used to update automatically when the actual hours worked
for a task in the main plan exceeds the allocated work hours ?
For reference I'm using MSP 2007 with fixed units tasks.
thanks
Mark