toast88
I have a project that will have 5 phases with phases overlapping (Phase 1
overlaps w/ #2, #2 overlaps with #3, etc..). I need to build in resource and
schedule contingency planning per phase. Any suggestions/experiences on the
best way to do so since there is no clean cutoff that one phase must be done
before the other can start?
My initial thoughts are to setup a task per phase and assign resources to
the task for the desired duration of the contingency amount of the phase.
Any thoughts from you on your experience is appreciated.
Thanks!
overlaps w/ #2, #2 overlaps with #3, etc..). I need to build in resource and
schedule contingency planning per phase. Any suggestions/experiences on the
best way to do so since there is no clean cutoff that one phase must be done
before the other can start?
My initial thoughts are to setup a task per phase and assign resources to
the task for the desired duration of the contingency amount of the phase.
Any thoughts from you on your experience is appreciated.
Thanks!