B
Bob Inwater
I work in a schedule where I have to manually re-level the resources on a
daily basis. What I wish I could do is edit (contour / level) the resource
units for a given time period in the “Resource Units†view and have the
duration be recalculated based the original total Work.
As an example: a task originally uses 2 units for 3 weeks. Later we find
that we are going to only have 1 unit available in the second week but total
work is unchanged. If I go into “Resource Usage†and edit the units the
duration does not change and all I have done is decrease work. This problem
seems to be more or less the same regardless of what task type I use.
If there was a total work stoppage for a time period I could use a split but
generally what I have is resources being shifted back and forth. I also do
not use splits much since I almost exclusively edit in “Resource Usageâ€.
Ideas?
Thanks
daily basis. What I wish I could do is edit (contour / level) the resource
units for a given time period in the “Resource Units†view and have the
duration be recalculated based the original total Work.
As an example: a task originally uses 2 units for 3 weeks. Later we find
that we are going to only have 1 unit available in the second week but total
work is unchanged. If I go into “Resource Usage†and edit the units the
duration does not change and all I have done is decrease work. This problem
seems to be more or less the same regardless of what task type I use.
If there was a total work stoppage for a time period I could use a split but
generally what I have is resources being shifted back and forth. I also do
not use splits much since I almost exclusively edit in “Resource Usageâ€.
Ideas?
Thanks