pheslar
I have had the request to determine if it is possible to contour work and
allow Project to evenly spread the remaining work. For example, Resource 1
has 100 hours of work over the course of 100 working days. The PM would like
to contour, specifying that Resource 1 will work 10 hours on this task on
January 1, and have Project:
1) Leave the Work at 100 hours
2) Spread the remaining 90 hours evenly over the other 99 working days
(without having to type in the remaining fractional hours into each column).
Is this possible? I know you can “un-contour†by changing the assignment
back to Flat, but this changes the work on the day you just typed in as well.
allow Project to evenly spread the remaining work. For example, Resource 1
has 100 hours of work over the course of 100 working days. The PM would like
to contour, specifying that Resource 1 will work 10 hours on this task on
January 1, and have Project:
1) Leave the Work at 100 hours
2) Spread the remaining 90 hours evenly over the other 99 working days
(without having to type in the remaining fractional hours into each column).
Is this possible? I know you can “un-contour†by changing the assignment
back to Flat, but this changes the work on the day you just typed in as well.