H
HDLF
I am resource loading a task that is contracted out. I'm
using the method recommended in T. Pyron's Book (fixed
duration task, associate a vendor resource, set units to
zero, enter cost). The problem is that MS Project enters
the ENTIRE cost at the beginning of the task. Since the
task has a duration is there any way to make MS Project
spread the cost over of the duration of the task? I
thought of using a fixed cost, but then I'd lose the
association with the vendor. Any help would be greatly
appreciated.
using the method recommended in T. Pyron's Book (fixed
duration task, associate a vendor resource, set units to
zero, enter cost). The problem is that MS Project enters
the ENTIRE cost at the beginning of the task. Since the
task has a duration is there any way to make MS Project
spread the cost over of the duration of the task? I
thought of using a fixed cost, but then I'd lose the
association with the vendor. Any help would be greatly
appreciated.