Control sort order of "Task" items in Timesheet view

J

Joe

Why is the order of task assignments in the Timesheet view not in the same
order of the project plan itself? For example, task “A†is in the plan to
start on 1/3 and task “B†to start on 1/10 (there is a link between the two
task). These two tasks are from 2 separate summary task items. Yet the view
shows them in reverse order in the Timesheet view and I can’t seem to control
this. The only thing I did notice is they may be displayed alphabetically by
summary task name, but I don’t want this to be the case. I want it to be
displayed by the order of the Start date.

Any suggestions?
 
D

Dale Howard [MVP]

Joe --

In the PWA timesheet, click the Start date column header until you see a
little gray arrow pointing up. It sounds like you may have accidentally
clicking another of the column headers, which applies sorting based on the
data in the selected column. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top