I want to print my Gantt chart. Not only have I set the project's start date
to 2/1/2009 (in Project Information under Project menu), my first date of the
project (in the first task) is 2/1/2009.

However, when I preview or print the Gantt chart, it only prints from March
2007 to April 2008. These are months before my project starts, and there are
absolutely no tasks in these months.

How do I get Project to print the months I select for the Gantt chart?

Ed
 
D

Dale Howard [MVP]

Ed K --

In the Print dialog, you can see a Timescale section. Select your date
range there. Hope this helps.
 