Controlling the baseline with subprojects

F

Freisia

Hi Folks

If I have an active MasterPlan with multiple linked subprojects how can I
control the baseline if a Project manager decides to update it in his subplan?
 
R

Rod Gill

In Project 2003 (and 2002, tho I can't remember for sure) there are 10 extra
baselines available. Try having a standard where Baseline1 is always a copy
of the original baseline then PM's can reset the normal baseline whenever
they want. In fact I recommend resetting it every week for a very time
critical project so weekly progress be seen.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.project-systems.co.nz/
Email rodg AT project-systems DOT co DOT nz
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top