B
Bobg
Hello,
This may be a basic question to more experienced users, but until I get this
down I don't feel that I am using Project the most efficient way I can.
I am looking for the best way to let project work the way it is supposed to
and yet control the order of tasks when I want to. I have tried using
priorities combined with leveling and that seems to work some of the time,
but there are times when I am confused by what it does.
Here are two examples of the types of issues I am having:
1. Let's say I have 6 tasks that will be worked on by one resource (A1,A2,A3
and B1,B2,B3) where A1 is a predecessor to A2, A2 is a predecessor to A3,
etc. The same dependency holds true for the B tasks but there is no hard
dependency between the two sets of tasks. As a matter of preference, I would
like B1 to start when A3 is complete. I have tried setting higher priorities
to the A tasks but there are still times that project will schedule B tasks
to occur before the end of A3, even though they are a lower priority. I
suspect that priority is only related to leveling for over-allocations and
will not come into play for "regular" scheduling. Are my only options to
either create an artificial dependency or to edit the work schedule and force
things to the order that I would prefer?
2. Same scenario as 1 above but after leveling some tasks are placed WAY out
in the future for no apparent reason. Have checked constraint dates, actual
dates, etc. but cannot figure out why would happen. In the latest example,
the task in that was scheduled way out had a predecessor that finished 6
months before it and there was nothing scheduled for the resource for several
months before this task. Any ideas on things to look at in this case?
Thank you for your help,
Bob
This may be a basic question to more experienced users, but until I get this
down I don't feel that I am using Project the most efficient way I can.
I am looking for the best way to let project work the way it is supposed to
and yet control the order of tasks when I want to. I have tried using
priorities combined with leveling and that seems to work some of the time,
but there are times when I am confused by what it does.
Here are two examples of the types of issues I am having:
1. Let's say I have 6 tasks that will be worked on by one resource (A1,A2,A3
and B1,B2,B3) where A1 is a predecessor to A2, A2 is a predecessor to A3,
etc. The same dependency holds true for the B tasks but there is no hard
dependency between the two sets of tasks. As a matter of preference, I would
like B1 to start when A3 is complete. I have tried setting higher priorities
to the A tasks but there are still times that project will schedule B tasks
to occur before the end of A3, even though they are a lower priority. I
suspect that priority is only related to leveling for over-allocations and
will not come into play for "regular" scheduling. Are my only options to
either create an artificial dependency or to edit the work schedule and force
things to the order that I would prefer?
2. Same scenario as 1 above but after leveling some tasks are placed WAY out
in the future for no apparent reason. Have checked constraint dates, actual
dates, etc. but cannot figure out why would happen. In the latest example,
the task in that was scheduled way out had a predecessor that finished 6
months before it and there was nothing scheduled for the resource for several
months before this task. Any ideas on things to look at in this case?
Thank you for your help,
Bob