A
Andrea
Hello All,
The issue of a plan that was running with % Complete and
then transfers over to tracking hours. So, lets say it
was 50% complete and then they switch over to doing hours
and they put in 8 hours where they are in their schedule.
Let's say the task was 800 hours. Now the system, because
of the switch is saying it is 1/100th finished vs.
translating the 50% complete into 400 hours and then
adding the 8 to the 400 going forward.
Even still, the question was how is Project tracking that
change and if you wanted to go from one to the other, how
do you get the %complete to properly translate into hours
after the conversion, etc. And how is it possible for it
to tracking both in some plans?
Regards,
Andrea
The issue of a plan that was running with % Complete and
then transfers over to tracking hours. So, lets say it
was 50% complete and then they switch over to doing hours
and they put in 8 hours where they are in their schedule.
Let's say the task was 800 hours. Now the system, because
of the switch is saying it is 1/100th finished vs.
translating the 50% complete into 400 hours and then
adding the 8 to the 400 going forward.
Even still, the question was how is Project tracking that
change and if you wanted to go from one to the other, how
do you get the %complete to properly translate into hours
after the conversion, etc. And how is it possible for it
to tracking both in some plans?
Regards,
Andrea