H
Hadi
Hello,
I'm looking for some expert advice on how to go about this. I have about 50
project schedules that are saved to the project server 2003 but all have
local resources. I have about 40 resources but only about 10 are actually
assigned to these projects. Now, I need to create the same resources in the
enterprise resource pool, switch the assignments using the enterprise
resources on my projects, and then eliminate the local resources.
any particular recommendations on how to go about this as efficiently as
possible. is there any documentation about this?
Thank you,
Hadi
I'm looking for some expert advice on how to go about this. I have about 50
project schedules that are saved to the project server 2003 but all have
local resources. I have about 40 resources but only about 10 are actually
assigned to these projects. Now, I need to create the same resources in the
enterprise resource pool, switch the assignments using the enterprise
resources on my projects, and then eliminate the local resources.
any particular recommendations on how to go about this as efficiently as
possible. is there any documentation about this?
Thank you,
Hadi