Every so often, a customer will ask to have the schedule delivered as a
stand-alone schedule instead of a master and subproject files. I think at one
time, you could just send the consolidated schedule, fully expanded and all
the data was there for viewing. Now when you send the consolidated schedule,
subproject files are collapsed, so you can't see the data without the files.
Saving the consolidated schedule as an xml or mpd has the same result.
I have previously used Excel to realign the predecessors and successors, but
will need to recreate that process. I have considered saving the file to
Access opening it it Artemis, then exporting from Artemis back to Project.
Does anyone have any recommendations?
stand-alone schedule instead of a master and subproject files. I think at one
time, you could just send the consolidated schedule, fully expanded and all
the data was there for viewing. Now when you send the consolidated schedule,
subproject files are collapsed, so you can't see the data without the files.
Saving the consolidated schedule as an xml or mpd has the same result.
I have previously used Excel to realign the predecessors and successors, but
will need to recreate that process. I have considered saving the file to
Access opening it it Artemis, then exporting from Artemis back to Project.
Does anyone have any recommendations?