What's the best way to track "Converted Hours" (actual labor hours w/ actual
labor rates compared to baseline hours with baseline labor cost) and "Average
Labor Rates" per day and/or task.
 
G

Gérard Ducouret

Hi justanewbee,

Display the Earned Value table : View / Tables / More tables / Earned value
and look at the definition of the following fields:
- BCWS
- BCWP
- ACWP
Nb : hoover the mouse pointer over the column caption.

Hope this helps

Gérard Ducouret
 
J

Jim Aksel

Adding to Gerard's post -- be sure to post your actual values in the
"Actuals" columns such as "Actual Cost", "Actual Start" .... Also, go to
Tool/Options/Calculations and make sure to turn off Project ... you want to
calculate costs manually.
--
If this post was helpful, please consider rating it.

Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top