H
hessi
Hello there,
I'm trying to manage a 1-year project with about 5000 tasks and ca. 30
Resources.
The main goal of using MS Project is to keep track of delays due to
task dependencies, so each task has a fixed duration, but might get
moved due to changes on predecessors.
Around 60% of the tasks have resources allocated to them, but not to
manage getting the tasks done but simply to know (roughly) what a
member of my team is doing at the moment. Hence, I don't really care
whether a task is allocated to him during his vacation or he has an 18
hour day according to Project, as long as it's not 0 hours for weeks
at a time.
Unfortunately, Project tries to "help" me by doing some automatic
stuff as soon as I change something.
I managed to get rid of the change of duration after adding/removing
resources by changing all tasks from Type: Fixed Units to Type: Fixed
Duration. Furthermore, I switched off Effort Driven - I still don't
know for sure what it does, but it seems to avoid some automation, and
that's fine by me.
My current problem is that MS Project changes the duration of a task
(and sometimes a few other tasks in the process) after I change
something on a Predecessor, while giving me the error message:
"The resource is assigned outside the original dates for task [...].
The duration of this fixed-duration task will change to accommodate
the resource assignment"
Unfortunately, it doesn't keep track of the old duration, so I can't
change it back if I don't know what it was... not good.
Searching in this group, I found some hints on changing the Type from
Fixed Duration to Fixed Units or Fixed Work, but that seems
counterproductive to the issue I had in the first place.
After some playing around, I found out that the error message doesn't
appear if I change every task to the Standard Calendar and switch on
"Scheduling ignores resource calendars".
I'm not sure though what other effects this might have on my file. It
still seems to link my resource usage to the tasks and even marks
resources in red which are overbooked (once again, doesn't really
matter, but good to know).
So, is this the right way for me to go or what would you propose to
get rid of the "help" MS Project tries to give me?
Thanks.
Best Regards
Christian Hessmann
I'm trying to manage a 1-year project with about 5000 tasks and ca. 30
Resources.
The main goal of using MS Project is to keep track of delays due to
task dependencies, so each task has a fixed duration, but might get
moved due to changes on predecessors.
Around 60% of the tasks have resources allocated to them, but not to
manage getting the tasks done but simply to know (roughly) what a
member of my team is doing at the moment. Hence, I don't really care
whether a task is allocated to him during his vacation or he has an 18
hour day according to Project, as long as it's not 0 hours for weeks
at a time.
Unfortunately, Project tries to "help" me by doing some automatic
stuff as soon as I change something.
I managed to get rid of the change of duration after adding/removing
resources by changing all tasks from Type: Fixed Units to Type: Fixed
Duration. Furthermore, I switched off Effort Driven - I still don't
know for sure what it does, but it seems to avoid some automation, and
that's fine by me.
My current problem is that MS Project changes the duration of a task
(and sometimes a few other tasks in the process) after I change
something on a Predecessor, while giving me the error message:
"The resource is assigned outside the original dates for task [...].
The duration of this fixed-duration task will change to accommodate
the resource assignment"
Unfortunately, it doesn't keep track of the old duration, so I can't
change it back if I don't know what it was... not good.
Searching in this group, I found some hints on changing the Type from
Fixed Duration to Fixed Units or Fixed Work, but that seems
counterproductive to the issue I had in the first place.
After some playing around, I found out that the error message doesn't
appear if I change every task to the Standard Calendar and switch on
"Scheduling ignores resource calendars".
I'm not sure though what other effects this might have on my file. It
still seems to link my resource usage to the tasks and even marks
resources in red which are overbooked (once again, doesn't really
matter, but good to know).
So, is this the right way for me to go or what would you propose to
get rid of the "help" MS Project tries to give me?
Thanks.
Best Regards
Christian Hessmann