Copy Internal Links when Copying a Summary Tasks

R

Rob Schneider

That's an interesting question that I don't know the answer for. I do
know that how you select tasks for copying (correct way is to select the
"ID" field to get all information held about the task) is important.
Further, based on my experimentation right now, you have to copy the
selected task when the subtasks are not opened. Project takes all the
subtasks (apparently) when subtasks re nowt show. Then, how you point to
the destination location makes a different. Simply pointing to a task
name work. You should select the target row by clicking your mouse
pointer on the ID field.

Also, if this behaviour is happening differently in different files, it
might be how could be set for linking different (See Menu:
Tools/Options, Tab: Schedule, then see "auto link inserted or moved
tasks". (I didn't experiment with that).

--rms

www.rmschneider.com
 
B

Barak Bester

I have found out that if the project is saved to the server (2007) the links are NOT copied, and if the project is saved locally the links do get copied.

I need the links to get copied also on the server.

How?

10x,
Barak



Barak Bester wrote:

Copy Internal Links when Copying a Summary Tasks
18-Jan-10

In some projects, when I copy a summary task it copies the links between its subtasks.

In others, the links are not copied.

What controls if the links are copied or not?

10x,
Barak

Previous Posts In This Thread:


Submitted via EggHeadCafe - Software Developer Portal of Choice
Use HTTP PUT Client to Upload Binary and Text Data
http://www.eggheadcafe.com/tutorial...8-4eb0d49d899c/use-http-put-client-to-up.aspx
 
R

Rob Schneider

That's an interesting question that I don't know the answer for. I do
know that how you select tasks for copying (correct way is to select the
"ID" field to get all information held about the task) is important.
Further, based on my experimentation right now, you have to copy the
selected task when the sub-tasks are not opened. Close them up. Project
takes all the sub-tasks (apparently) when sub-tasks re not shown. Then,
how you point to the destination location makes a difference. Simply
selecting a task name won't work. You should select the target row by
clicking your mouse pointer on the ID field.

Also, if this behaviour is happening differently in different files, it
might be affected by how linking is set--see Menu: Tools/Options, Tab:
Schedule, then see "auto link inserted or moved tasks". (I didn't
experiment with that).

--rms

www.rmschneider.com
 