M
M Colodzin
Hi,
I'm working on a project that has a 3500+ line MSP 03 project schedule.
We've have encountered a serious file bloat problem that causes the file to
grow by approximately 10x each time we create a new baseline.
We've experimented with copying and pasting the baseline columns as follows:
- highlight Baseline Duration column and hit Cntrl-C to capture the data
- highlight the Baseline1 Duration column and hit Cntrl-V to paste the data
- repeat the process for the other baseline fields
We then copy the Duration column into the Baseline Duration column, etc...
to create a new baseline for the entire schedule.
I realize that this is not the same as using the Tools -> Tracking -> Save
Baseline process and that it does not update all of the baseline tables in
the database.
However, using this copy/paste process does not cause the file size to grow
signficantly.
My question is: what are the implications of performing this copy/paste
process vs. using the formal baseline process. If we only use the baseline
data to compare against our start, finish, duration and work values, is this
a safe process to avoid the file bloat problem we've been experiencing?
If not, what problems can we anticipate?
Thanks!!
I'm working on a project that has a 3500+ line MSP 03 project schedule.
We've have encountered a serious file bloat problem that causes the file to
grow by approximately 10x each time we create a new baseline.
We've experimented with copying and pasting the baseline columns as follows:
- highlight Baseline Duration column and hit Cntrl-C to capture the data
- highlight the Baseline1 Duration column and hit Cntrl-V to paste the data
- repeat the process for the other baseline fields
We then copy the Duration column into the Baseline Duration column, etc...
to create a new baseline for the entire schedule.
I realize that this is not the same as using the Tools -> Tracking -> Save
Baseline process and that it does not update all of the baseline tables in
the database.
However, using this copy/paste process does not cause the file size to grow
signficantly.
My question is: what are the implications of performing this copy/paste
process vs. using the formal baseline process. If we only use the baseline
data to compare against our start, finish, duration and work values, is this
a safe process to avoid the file bloat problem we've been experiencing?
If not, what problems can we anticipate?
Thanks!!