Copy pasting and leveling tasks

A

anonymous

I know MSPJ may encounter errors when pasting tasks from
existing workplans (especially those with actual data) to
new ones, so we decided only to copy only task names and
paste them to a blank workplan.

All tasks paste properly, but they all have the same
outline level, so all of the previous task
indenting/outdenting disappeared.

I KNOW I was able to do this previously, but for the life
of me I forgot: How or what do you copy that will allow
the tasks to re-level themselves like the previous
workplan? I thought it was the Outline Level column, but
copy-pasting that doesn't work, for some reason the data
won't paste. WBS doesn't adjust the task levels. Would
greatly appreciate some help.
 
M

Mike Glen

Hi anonymous,

Welcome to this Microsoft Project newsgroup :)

Why not take a copy of you existing project, delete all existing actuals and
all tasks/resources you don't want, and use that as the "template" for your
new project?

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top