Hi all project experts
We have a MSProject 2003 installation, where one project do some tricky stuff.
We had one project which was saved under a new name. Now in the timesheet
website, all task have 0 hour work for all days. The total is fine though
I tried republish tasks, but this wont fill in on which days who used how
many hours. Only the total is displayed in the timesheet view.

Now. If I open the project from the MS project 2003 office application, I
can see on which days how many hours is registred.

How can this be, and can I update the timesheet view somehow?

Thanks
Christian
 
D

Dale Howard [MVP]

Ennova --

Open the project in question and then do the following:

1. Click Collaborate - Publish - Republish Assignments.
2. Select the "Overwrite actual work entered by resources" option.
3. Click the OK button.

The above steps will "push" the actuals from the Microsoft Project plan to
each resource's View My Tasks page in PWA. Hope this helps.
 